Hi, I just installed the trial version of beCPG software and seeing its working.
I created a project. When I try to change the due date for the project, the changed date doesn't show up.
Also, how can I change the project code? Its not editable in the edit properties box.
Thanks!
Hello,
Due date filled : mode is retro planning (start date is calculated automatically from the due date)
Due date empty : mode is planning (completed date is calculated automatically from the start date)
Project code is read only property calculated by beCPG. You can use the property name to codify your project manually.